KUALA TERENGGANU: The construction progress of the East Coast Rail Link (ECRL) project in Terengganu has reached 55.21%, says Malaysia Railway Link Sdn Bhd.
Its chief executive officer Datuk Seri Darwis Abdul Razak said the construction of the 275km-long alignment is on schedule and is expected to be completed by December 2026.
It involves the building of four passenger stations in Jerteh, Bandar Permaisuri, Kuala Terengganu and Kemasik, while the stations in Dungun and Chukai will be used for both passenger and cargo purposes. “Construction work for the entire 665km ECRL line from Kota Baru of Kelantan to Port Klang in Selangor is at a progress level of 40.81%.
“The 275km route in Terengganu is the longest compared to the other three states – Kelantan, Pahang and Selangor,” Darwis said at a breaking of the fast event with ECRL workers here on Sunday, Bernama reported.
United States Latest News, United States Headlines
Similar News:You can also read news stories similar to this one that we have collected from other news sources.
MRL: Progress of construction work of ECRL project in Terengganu has reached more than 50pcKUALA TERENGGANU, April 3 — The progress of the construction work of the East Coast Rail Link (ECRL) Project in Terengganu has reached 55.21 per cent, said Malaysia Railway Link...
Read more »
Pembinaan ECRL di Terengganu capai tahap 55.21 peratusStesen Jerteh di Besut , Bandar Permaisuri (Setiu), Kuala Terengganu dan Kemasik (Kemaman) telah ditetapkan sebagai stesen penumpang manakala stesen Dungun dan Chukai di Kemaman adalah stesen untuk penumpang dan kargo.
Read more »
MRL: Progress of ECRL Project in T’ganu more than 50%He said construction of the 275-kilometre-long alignment in the state is on schedule and is expected to be fully completed in December 2026. theSun thesundaily ECRL MRL Terengganu construction
Read more »
Jalan Kuala Terengganu-Kuantan closed for ECRL works - April 4-7, 9am to 12.30pm and 2pm to 5pm - paultan.orgClick to enlarge Dungun district police have announced that there will be a road closure at Jalan Kuala Terengganu-Kuantan, specifically at Durian Mentangau on the T118. The full closure to all traffic will be from …
Read more »
Tiada doktor kontrak di Terengganu lakukan mogokPerkhidmatan kesihatan awam di semua enam hospital dan klinik kesihatan di Terengganu berjalan lancar seperti biasa selepas tiada doktor kontrak di negeri ini melakukan Mogok Doktor Malaysia yang dijadual diadakan selama tiga hari bermula hari ini.
Read more »