Kusile repairs: How much? Who knows?

United States News News

Kusile repairs: How much? Who knows?
United States Latest News,United States Headlines
  • 📰 BDliveSA
  • ⏱ Reading Time:
  • 63 sec. here
  • 3 min. at publisher
  • 📊 Quality Score:
  • News: 28%
  • Publisher: 63%

Eskom has spent R250m so far on the construction of temporary stacks at the plant

Eskom does not yet know what it will cost to make permanent repairs at Kusile power station in Mpumalanga where three generation units were taken offline after a big breakdown in October.

In October last year a 9m diameter flue gas desulphurisation duct, which carries emissions from unit 1 into a large chimney, collapsed under the weight of ash build-up inside the pipe. The chimney also houses the flue gas ducts for units 2 and 3. As a result all three units — with a combined generation capacity of 2,100MW — had to be shut down, contributing to two full stages of load-shedding.

However, he said, the temporary repairs for units 1, 2 and 3 are on track to be completed by December 24. Unit 5, which has not yet been commissioned, should be “fully running” by April 2024. Together this will add about 3,200MW of generation capacity, enough to mitigate three stages of load-shedding.“Kusile is particularly important to the resolution of load-shedding in the country. If the three units were operating today, they could each give us about 800MW,” said Ramokgopa.

It allows the utility to build and operate temporary stacks for units 1, 2 and 3 without the use of the flue gas desulphurisation mechanism for 13 months. This is likely to result in increases in sulphur dioxide emissions, a step which environmental groups have warned will have major health consequences for people living near the power station.

We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

BDliveSA /  🏆 12. in ZA

United States Latest News, United States Headlines

Similar News:You can also read news stories similar to this one that we have collected from other news sources.

Welcome to Eskom MegaGravy Train Park - TechCentralWelcome to Eskom MegaGravy Train Park - TechCentralEskom’s head office, Megawatt Park, has been renamed “Eskom MegaGravy Train Park” on Google Maps.
Read more »

SA feels wrath of Kusile’s dark dawn as energy crisis bites hardMpumalanga's Kusile power station should have relieved South Africa's energy generation pressures in 2013. However, a decade later it finds itself among the causes of the country's crippling winter energy woes.
Read more »

Electricity Minister visits Kusile againElectricity Minister visits Kusile againElectricity Minister Kgosientsho Ramokgopa is visiting the Kusile Power Station in Delmas. He wants a status report on measures taken to bring back four units.
Read more »

Kusile Power Station: Repairs on track, fully operational by April 2024 | The CitizenKusile Power Station: Repairs on track, fully operational by April 2024 | The Citizen📣💡Electricity minister Kgosientsho Ramokgopa confirms significant strides at KusilePowerStation. Here's when unit 5 will be fully operational 🔌 TheCitizenNews Eskom loadshedding Find out more⬇️
Read more »

Eskom spent R500 million on three-month security dealEskom spent R500 million on three-month security dealThe City Press alleges that Eskom paid the Fidelity Services Group R500 million over a three-month period to provide security and collect intelligence at Eskom infrastructure across South Africa.
Read more »

Couple implicated in Eskom corruption ambushed | City PressCouple implicated in Eskom corruption ambushed | City PressA couple from Mpumalanga who are on the radar of the SIU related to a R400 million Eskom contract, is in hiding – not from the crime-busting agency’s investigators, but from hired assassins who allegedly ambushed them early this month
Read more »



Render Time: 2025-03-07 03:19:33