Koeberg 1’s planned availability during winter is off the table | The Citizen

United States News News

Koeberg 1’s planned availability during winter is off the table | The Citizen
United States Latest News,United States Headlines
  • 📰 TheCitizen_News
  • ⏱ Reading Time:
  • 42 sec. here
  • 2 min. at publisher
  • 📊 Quality Score:
  • News: 20%
  • Publisher: 75%

Koebergs new target date of 13 September is a full 90 days after the original date of 8 June, when the 180-day outage was supposed to end. nuclear loadshedding Full story here ➡️

It said: “The first steam generator has been removed from the containment building and placed in the storage building that was erected to house the steam generators. This is a significant accomplishment for the

The original plan was to have both units in service during the winter months to limit load shedding as demand increases, and to start the outage on Unit 2 in September. If the extension project in one of the two units is not completed by mid-2024 when Koeberg’s licence expires, it will be switched off and Eskom will have to apply for a new licence from scratch.What exactly the reason is for the delay in the current outage, is not clear. Eskom refers in its statement to “some unexpected challenges during the execution in the current outage” but fails to give any detail.

He also asked not to be named and said the reason Eskom battles to stick to outage deadlines may be that it has only the two nuclear units. A bigger fleet would have allowed Eskom to gain more experience and deliver better results.

We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

TheCitizen_News /  🏆 6. in ZA

United States Latest News, United States Headlines

Similar News:You can also read news stories similar to this one that we have collected from other news sources.

The Citizen columnist Cliff Buchler dies aged 84 | The CitizenThe Citizen columnist Cliff Buchler dies aged 84 | The CitizenIn 1978 Cliff Buchler established Roodepoort Record (among others since) and remained managing editor for more than 30 years.
Read more »

Koeberg 1’s planned availability during winter is off the tableKoeberg 1’s planned availability during winter is off the tableMinister of Electricity Kgosientsho Ramokgopa faces increasing loadshedding worries as Koeberg 1 will be offline until at least September. Moneyweb Eskom
Read more »

Blow the whistle: How the corrupt use legal tactics to retaliate againBlow the whistle: How the corrupt use legal tactics to retaliate againJoin markwheywood in this critical discussion about the legal retaliation tactics used against whistleblowers. They will expose how the law has been used against whistleblowers who seek to uphold ethics, accountability, and public integrity.
Read more »

Blow the whistle: How the corrupt use legal tactics to retaliate againBlow the whistle: How the corrupt use legal tactics to retaliate againHow do we navigate corruption in the workplace? How panel of experts provide both the legal and HR perspectives to deal with intimidation against whistleblowers. Join us in the live room:
Read more »

Horse-trading at Ekurhuleni council as another motion looms | The CitizenHorse-trading at Ekurhuleni council as another motion looms | The CitizenIs Ekurhuleni Mayor Tania Campbell on her way out? There will be frantic behind-the-scenes negotiations to try and salvage what appears to be a no-win situation for her. Full story here ➡️
Read more »

Thabo Bester saga shows clear levels of corruption | The CitizenThabo Bester saga shows clear levels of corruption | The CitizenTheCitizen Editorial: Horrifying as the story is, it would not have been exposed had it not been for the tireless efforts of the GroundUp news organisation – it is more confirmation that our criminal justice system is beyond saving. Read more here:
Read more »



Render Time: 2025-04-07 14:29:28